An approach for optimal units start-up during bulk power system restoration

Ketabi, A ; Sharif University of Technology | 2001

103 Viewed
  1. Type of Document: Article
  2. DOI: 10.1109/LESCPE.2001.941649
  3. Publisher: Institute of Electrical and Electronics Engineers Inc , 2001
  4. Abstract:
  5. This paper describes an approach for unit start-up sequence determination during power system restoration. This approach is based on the backtracking search method, which determines the generating starting times to maximize the MWh load served over a restoration period and guarantee optimality of the start up sequence. The dynamic characteristics of different types of units and system constraints have to be considered. The shortest path, i.e., the path that requires the minimal number of switching actions, between the supplying unit and load is selected unless it is not feasible. Simulation tests, carried out on 39-bus New England test system, verify the effectiveness of the proposed method. © 2001 IEEE
  6. Keywords:
  7. Backtracking Search method ; Generation Capability Dispatch ; Power System Restoration
  8. Source: 2001 Large Engineering Systems Conference on Power Engineering, LESCOPE 2001, 11 July 2001 through 13 July 2001 ; 2001 , Pages 190-194 ; 0780371070 (ISBN); 9780780371071 (ISBN)