    A polynomial time branch and bound algorithm for the single item economic lot sizing problem with all units discount and resale [electronic resource]

    , Article International Journal of Optimization in Civil Engineering ; 2012, 2(2): 183-202 Mirmohammadi, S. H. (S. Hamid) ; Shadrokh, Sh ; Eshghi, Kourosh ; Sharif University of Technology
    Abstract
    The purpose of this paper is to present a polynomial time algorithm which determines the lot sizes for purchase component in Material Requirement Planning (MRP) environments with deterministic time-phased demand with zero lead time. In this model, backlog is not permitted, the unit purchasing price is based on the all-units discount system and resale of the excess units is possible at the ordering time. The properties of an optimal order policy are argued and on the basis of them, a branch and bound algorithm is presented to construct an optimal sequence of order policies. In the proposed B&B algorithm, some useful fathoming rules have been proven to make the algorithm very efficient. By... 

    Solving the resource availability cost problem in project scheduling by path relinking and genetic algorithm

    , Article Applied Mathematics and Computation ; Volume 196, Issue 2 , 2008 , Pages 879-888 ; 00963003 (ISSN) Ranjbar, M ; Kianfar, F ; Shadrokh, S ; Sharif University of Technology
    2008
    Abstract
    This paper considers a project scheduling problem with the objective of minimizing resource availability costs required to execute the activities in a project by a given project deadline. The project contains activities interrelated by finish-start-type precedence relations with a time lag of zero, which require a set of renewable resources. Two metaheuristics, path relinking and genetic algorithm, are developed to tackle this problem in which a schedule is created with a precedence feasible priority list given to the schedule generation scheme. In these procedures, each new generation of solutions are created using the combination of current solutions. Comparative computational results... 

    Strategic alignment: ITIL perspective

    , Article ICCTD 2010 - 2010 2nd International Conference on Computer Technology and Development, Proceedings, 2 November 2010 through 4 November 2010 ; November , 2010 , Pages 550-555 ; 9781424488438 (ISBN) Bagher Esmaili, H ; Gardesh, H ; Shadrokh Sikari, S ; Sharif University of Technology
    2010
    Abstract
    The literature suggests that organizations cannot be competitive if their business and information technology strategies are not aligned. Yet achieving strategic alignment continues to be a major concern for business executives. A number of alignment models have been offered in the literature, primary among them the Strategic Alignment model (SAM) and IT Governance (via ITIL). As there is no published research that attempts to present how effective ITIL V3 is to align business and IT in strategic level, this paper reports on determining aligning roles of ITIL by applying it to the SAM framework. In this regard, the (TIL Strategic Alignment model is proposed to describe ITIL V3 approach of... 

    Validating ITIL maturity to strategic business-IT alignment

    , Article ICCTD 2010 - 2010 2nd International Conference on Computer Technology and Development, Proceedings, 2 November 2010 through 4 November 2010 ; November , 2010 , Pages 556-561 ; 9781424488438 (ISBN) Bagher Esmaili, H ; Gardesh, H ; Shadrokh Sikari, S ; Sharif University of Technology
    2010
    Abstract
    Ensuring that organizational IT is in alignment with and provides support for an organization's business strategy is critical to business success. As there is no published research that attempts to describe maturity of ITIL V3 in aligning business and IT at strategic level, this paper reports on determining aligning roles of ITIL V3 in practice. In this paper, ITIL maturity to business-IT strategic alignment is validated by Strategic Alignment Maturity model. Focusing on how ITIL V3 covers business-IT alignment maturity criteria of the model, the maturity of ITIL strategic alignment practices is assessed which makes it possible to recognize conceptual and practical competencies of ITIL to... 

    Strategic alignment: ITIL perspective

    , Article Proceedings of the International Conference on Electronic Business (ICEB), 1 December 2010 through 4 December 2010, Shanghai ; 2010 , Pages 457-462 ; 16830040 (ISSN) Bagher Esmaili, H ; Gardesh, H ; Shadrokh Sikari, S ; Sharif University of Technology
    2010
    Abstract
    The literature suggests that organizations cannot be competitive if their business and information technology strategies are not aligned. Yet achieving strategic alignment continues to be a major concern for business executives. A number of alignment models have been offered in the literature, primary among them the Strategic Alignment model (SAM) and IT Governance (via ITIL). As there is no published research that attempts to present how effective ITIL V3 is to align business and IT in strategic level, this paper reports on determining aligning roles of ITIL by applying it to the SAM framework. In this regard, the ITIL Strategic Alignment model is proposed to describe ITIL V3 approach of... 

    Project buffer sizing and dynamic buffer consumption algorithm in power generation construction

    , Article Engineering, Construction and Architectural Management ; Volume 29, Issue 2 , 2022 , Pages 716-738 ; 09699988 (ISSN) Zohrehvandi, S ; Khalilzadeh, M ; Amiri, M ; Shadrokh, S ; Sharif University of Technology
    Emerald Group Holdings Ltd  2022
    Abstract
    Purpose: The aim of this research is to propose a buffer sizing and buffer controlling algorithm (BSCA) as a heuristic algorithm for calculating project buffer and feeding buffers as well as dynamic controlling of buffer consumption in different phases of a wind power plant project in order to achieve a more realistic project duration. Design/methodology/approach: The BSCA algorithm has two main phases of planning and buffer sizing and construction and buffer consumption. Project buffer and feeding buffers are determined in the planning and buffer sizing phase, and their consumption is controlled in the construction and buffer consumption phase. The heuristic algorithm was coded and run in... 

    A fuzzy project buffer management algorithm: a case study in the construction of a renewable project

    , Article International Journal of Construction Management ; 2022 ; 15623599 (ISSN) Zohrehvandi, S ; Vanhoucke, M ; Khalilzadeh, M ; Amiri, M ; Shadrokh, S ; Sharif University of Technology
    Taylor and Francis Ltd  2022
    Abstract
    One of the major problems with projects is that they are not completed according to schedule. Uncertainty always exists at the heart of real-world project scheduling problems. This paper introduces a fuzzy project buffer management (FPBM) algorithm which is a combination of the adaptive procedure with resource tightness (APRT) and fuzzy failure mode and effects analysis (FFMEA) methods. This paper aims to present an efficient model for project buffer sizing by taking FFMEA into account to reach a more realistic schedule. In this research, for increasing the efficiency of the APRT method, the FFMEA technique is simultaneously applied with them. This research was carried out as a case study in... 

    A modified PSO algorithm for minimizing the total costs of resources in MRCPSP

    , Article Mathematical Problems in Engineering ; Volume 2012 , 2012 ; 1024123X (ISSN) Khalilzadeh, M ; Kianfar, F ; Shirzadeh Chaleshtari, A ; Shadrokh, S ; Ranjbar, M ; Sharif University of Technology
    2012
    Abstract
    We introduce a multimode resource-constrained project scheduling problem with finish-to-start precedence relations among project activities, considering renewable and nonrenewable resource costs. We assume that renewable resources are rented and are not available in all periods of time of the project. In other words, there is a mandated ready date as well as a due date for each renewable resource type so that no resource is used before its ready date. However, the resources are permitted to be used after their due dates by paying penalty costs. The objective is to minimize the total costs of both renewable and nonrenewable resource usage. This problem is called multimode resource-constrained... 

    Material Ordering in a Deterministic Time-Phased Demand Environment with All-Units Discount in Purchasing

    , Ph.D. Dissertation Sharif University of Technology Mirmohammadi, Hamid (Author) ; Shadrokh, Shahram (Supervisor)
    Abstract
    More than 60% of sales account for materials, and so the roles and responsibilities of the material managers have been recognized as more important within a firm or in a large scale project than before. However, in many purchasing situations, different considerations conflict with one another. In these situations material planning plays an essential role in the total cost minimization process. Here, the optimal material ordering policy for an item in a deterministic time-phased demand environment with all-units discount in purchasing is considered. Based on proven properties of the optimal order policy, a tree search procedure is designed to construct sequences of orders in the optimal... 

    Design of Business Processes for a Company that Offers IT Products and Services

    , M.Sc. Thesis Sharif University of Technology Salehi, Javad (Author) ; Shadrokh, Shahram (Supervisor)
    Abstract
    Small and medium companies generally start with a technical idea and usually without any specific strategy and mission . Commonly at this time short-term goals determine activities and current processes of company. As the time after time that the company grows it faces great problems because of the lack of strategy and long-term goals and also lack of correct definition of business processes. In this thesis with selecting one of these companies that provides products and services in information technology fields, after investigating current situation and problems we will redefine the mission and objectives with strategic approach. Then we offer a suitable business model that fits company... 

    Feasibility study of Foam Concrete production

    , M.Sc. Thesis Sharif University of Technology Koohestani, Mostafa (Author) ; Shadrokh, Shahram (Supervisor)
    Abstract
    Foam concrete is a new covering layer that can be used for several purposes in civil constructions and because of its unique physical specifications, produces a light concrete in which is isolated against thermal conductivity ,with required strength and favorite quality.This cover is made of cement , sand ,water and foam(chemical substance that produces foam) . The foam is mixed with water in a special machine (mixer) with a high speed centrifugal rotation and produces very small stable bubbles called foam. While cement and sand are mixed in special mixer, makes a fluent concrete that can be used in place, metallic or plastic molds. After dehydration, in accordance with percentage of... 

    Optimization Shop Area in Construction Projrect

    , M.Sc. Thesis Sharif University of Technology Raissi, Asghar (Author) ; Shadrokh, Shahram (Supervisor)
    Abstract
    Resource investment problem is one of problems in project scheduling which concerns with gaining minimum cost for accomplishing a project in a given time. Tardiness permitted with penalty cost makes this problem close to real world. This dissertation studied constraint of resources by restricted resources and tried to gain optimal level of restricted resource and middle resources start and finish time. This problem also permits tardiness with penalty cost. In construction projects, beside renewable and Non-renewable resources, there are workshops in which part of the work to carry out an activity, is done. These workshops include welding workshops and forming workshops in piping projects,... 

    Scheduling on Parallel Machines with Preemption and Transportation Delays using a Particle Swarm Optimization (PSO)-Based Algorithm

    , M.Sc. Thesis Sharif University of Technology Shams, Hesam (Author) ; Shadrokh, Shahram (Supervisor)
    Abstract
    This research deals with the problem of scheduling independent preemptive jobs on identical parallel machines, to minimize the total completion time (makespan). The transportation of an interrupted job from a machine to another machine requires considering a constant transportation delay i.e., Pm|prmp(delay)| Cmax. This delay is called transportation delay. We propose a Mixed Integer Linear Programming formulation for the research problem in case of two machines i.e., P2|prmp(delay)| Cmax. Since the research problem is shown to be NP-hard, a particle swarm optimization (PSO) algorithm is applied to solve the problem approximately. Based on the frequency of using local search procedure, three... 

    A Project Portfolio Selection Method for Iranian Private Construction Companies

    , M.Sc. Thesis Sharif University of Technology Hamdieh, Hosna (Author) ; Shadrokh, Shahram (Supervisor)
    Abstract
    The construction industry is one of the main industries in Iran, and plays a fundamental role in Iran’s economy, because construction has impact on most of other industries by its vast value chain. Selecting right sets of projects is considerably crucial for construction organizations to successfully achieve their competitive advantages and corporate strategies. Due to limited resources and dynamic changes in Iran’s construction business environment, this kind of selection is quite challenging for construction organizations. Beside’s over hundreds of selection tools, techniques, and complex selection frameworks were developed or recommended by academics and practitioners to smooth the... 

    Exact and Metaheuristic Solution of Multi-skilled Project Scheduling Problem Considering Learning and Forgetting Effects on the Performance of Project Members

    , M.Sc. Thesis Sharif University of Technology Mehmanchi, Erfan (Author) ; Shadrokh, Shahram (Supervisor)
    Abstract
    The multi-mode resource-constrained project scheduling problem is one of the most complex and most widely used problems in the project scheduling knowledge area and operations research science. Recently, a new type of this problem which is called multi-skilled project scheduling problem has been introduced in the literature. The aim of MSPSP is to schedule the activities regarding the precedence relationships and multi-skilled human resource constraints in such a way that the need of each activity to a subset of skills should be met by the qualified employees. In this thesis, in addition to taking the constraints of the standard problem into account, we consider a state in which the... 

    Identify and Assessment of Project's Risks Based on PMBOK's Standard - Case Study: Construct an Aquaculture Site in Abadan

    , M.Sc. Thesis Sharif University of Technology Kamaei, Amin (Author) ; Shadrokh, Shahram (Supervisor)
    Abstract
    Risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on a project’s objectives. Identification and assessment of risk in a measurable way are so important for project managers to decide better. This thesis studies how to identify and assess the project’s risks in Fishery industry based on the Project management body of knowledge (PMBOK 2008) as a global standard. Constructing an aquaculture site in Abadan city has some risks which are identified in the first steps of the study and in the following steps these risks will be prioritized by the use of qualitative analysis and figured out which risks have major effects on projects objectives. In last step... 

    Optimization of Process Plant Layout and Pipe Routing

    , M.Sc. Thesis Sharif University of Technology Mehrizi, Rahil (Author) ; Shadrokh, Shahram (Supervisor)
    Abstract
    Process plants such as refineries and petrochemical plants are complex facilities consisting of equipment, piping systems, instruments, electrical systems, computers, and control systems. Process units design is mostly based on designer`s experience and design general criteria and standards. Using mathematical methods to optimize the design may have an effective role in cost reduction and it would give the designer some general view in case that the exact design is not applicable.
    Optimization of Process units is described in this study. This optimization includes the exact location of each equipment, nozzle, pipe rack and also pipe route layouts. Mixed integer linear programming (MILP)... 

    Presentation of a Model and Solving the Problem of Project Portfolio Selection Based on Project Scheduling using Two-Level NSGAII

    , M.Sc. Thesis Sharif University of Technology Jafari, Hossein (Author) ; Shadrokh, Shahram (Supervisor)
    Abstract
    This project aims to study a situation in which several projects must be selected. The decision makers should select a subset of these projects taking into account the limitation of resources and scheduling. Project selection models generally do not consider schedule of project activities as part of selection process. On the other hand, except the cases where only one project is under process in each period, prioritizing the selected projects is not optimal not considering their scheduling. Projects scheduling in project activities level may increase the complexity of decision making for portfolio selection and expand the area of search for selection of projects portfolio. Therefore, all the... 

    Designing an Algorithm for the Resource Investment Problem Considering Calendar

    , M.Sc. Thesis Sharif University of Technology Parvizi, Saeed (Author) ; Shadrokh, Shahram (Supervisor)
    Abstract
    Project scheduling problems can be divided into different categories which one of the most important of them is resource investment problem. In this problem we are faced with a time limit for completion but resources are available unlimitedly and can be allocated to the project by specific cost. One of the most important constraints in real problems is the times that resources are available. In this research, resource investment problem considering calendar for resources has been investigated. Since resource investment problem is NP-Hard, after a brief overview of the different solutions, we used genetic algorithm to solve this problem. For this purpose, after determining chromosome... 

    Risk Assessment of Power Plant Projects with Fuzzy Approach (Case study: Shirkooh Yazd Combined Cycle Power Plant)

    , M.Sc. Thesis Sharif University of Technology Pourmohammadi, Sahar (Author) ; Shadrokh, Shahram (Supervisor)
    Abstract
    In this research, the risks of power plant projects are assessed with fuzzy approach. For this purpose, "Shirkooh Yazd combined cycle power plant" is chosen as the case study. First, the risks of power plant projects before the contract and during project execution are identified. Then these risks are categorized in a hierarchical breakdown structure. Subsequently, required information is collected from experienced professionals using questionnaires that used as the input data for risk qualitative analysis. In qualitative analysis, the risk probability and its impacts (containing time, cost and quality) are described by qualitative terms. After scaling them, the amount of each risk is...